Total project cost: 166440557.00
Convert: EUR USD UAH
Approximate duration: 18 months

Brief description of the project:

Water supply - the construction of 2 water pipelines to the land plot of the industrial park is envisaged: The first one from the 300 mm water supply pipeline on Trudova Street and the second one from the 300 mm water supply pipeline on Vinnytske Highway. It is planned to lay the water supply network in the industrial park. Water disposal (sewerage) - construction of a gravity and 2 pressure sewerage collectors with the installation of 2 sewage pumping stations is envisaged.

Project objective:

Ensuring the arrangement and operation of the industrial park

Involved organizations:

Capital Construction Department of Khmelnytskyi City Council

Partners:

Municipal Institution «Khmelnytskyi Development Agency»

Target customer segment:

residents of Khmelnytskyi, employees of the industrial park, local authorities.

Contact

Organization: Municipal institution «Khmelnytskyi City Development Agency»
Email: [email protected]

Technical solution:

Construction of 2 water pipelines to the land plot of the industrial park: The 1st one from the 300 mm water supply pipeline on Trudova Street and the 2nd one from the 300 mm water supply pipeline on Vinnytske Highway. Construction of water supply network in the industrial park. Construction of a gravity and 2 pressure sewer collectors with the installation of 2 sewage pumping stations.

Contact

+38 (098) 040 17 28 Ukraine, Khmelnytskyi invest.khm.gov.ua

Opening hours

8.00 AM – 5.15 PM

Andrii Moshchanets

Acting Director of Khmelnytskyi City Development Agency

Ukraine, Khmelnytskyi +38 (098) 040 17 28 [email protected]